Bailing Facility Improvements #8030
BAILING FACILITY IMPROVEMENTS #8030
GRAND FORKS, ND
General work included removing the existing scale and constructing a new scale. Removing the existing scale required the removal of the scale, the scale foundation, scale house, existing pavement and underground drainage.
Installing the new scale consisting of installing new underground drainage (RCP Pipe, PVC Pipe, Inlets & Manholes), re-grading the site, installing a new foundation for the scale and building, installing the new scale, installing a pre-engineered metal building, electrical work, plumbing work, new site paving and landscaping.
The new scale is from Rice Lake weighing system and is 11’ x 70’ integrated with automated software from Wasteworks.
Throughout the project a temporary scale was installed and maintained operations at the landfill and ensure a seamless transition from the existing scale to the new scale building.
SOLUTIONS PROVIDER.
Industry leading partner providing upfront and creative solutions for all your building solutions needs while minimizing business disruptions from project inception to completion.