Ashtabula Wind Farm
ASHTABULA WIND I & II COLLECTOR SUBSTATIONS OTTER TAIL POWER COMPANY
BARNES COUNTY AND LUVERNE, NORTH DAKOTA
The Ashtabula wind farm is the largest wind farm in North Dakota and consists of 250 turbines.
Ashtabula I project consisted of the construction of the Barnes County Collector Substation including pier drilling, excavation, concrete, structural steel supports, high voltage accessories, aluminum bus duct, breakers, switches, arrestor, transformers and ground grid for the 131 turbines.
Ashtabula II is the 230/34.5 kV substation near Luverne, ND and consisted of building an entrance road to the substation pad and building up the pad which occupies approximately 5 acres. Work on this project also consisted of pier drilling, excavation, concrete, structural steel supports, high voltage accessories, aluminum bus duct, breakers, switches, arrestor, transformers and ground grid for the 80 turbines.
SOLUTIONS PROVIDER.
Industry leading partner providing upfront and creative solutions for all your building solutions needs while minimizing business disruptions from project inception to completion.